High School Renovations on Schedule

Turner Construction presents project update

The are on schedule and on budget, said representatives from Turner Construction Company at Monday's school board meeting.

Turner has billed 26 percent of the project's $35,560,000 budget and used 32 percent of its budgeted contingency money on the project so far.

The renovations is funded mainly by a levy voters approved in 2010. Federal stimulus money will pay a $5.6 million share of the cost.

Find out what's happening in Beachwoodwith free, real-time updates from Patch.

Video: April 2012 Renovations Update from Beachwood Schools

Renovations are in their second phase: adding a second story to the gym and adding a music suite. Turner Construction added the electricity is finished and ready to run the entire building from the gym's basement.

Find out what's happening in Beachwoodwith free, real-time updates from Patch.

Next, the 500 and 600-numbered wing will be renovated, then the 100-200 wing will be demolished and a new media center and north gym will be built.