The Beachwood High School renovations are on schedule and on budget, said representatives from Turner Construction Company at Monday's school board meeting.

Turner has billed 26 percent of the project's $35,560,000 budget and used 32 percent of its budgeted contingency money on the project so far.

The renovations is funded mainly by a levy voters approved in 2010. Federal stimulus money will pay a $5.6 million share of the cost.

Video: April 2012 Renovations Update from Beachwood Schools

Renovations are expected to end in time for the start of the 2013 school year.

Renovations are in their second phase: adding a second story to the gym and adding a music suite. Turner Construction added the electricity is finished and ready to run the entire building from the gym's basement.

Next, the 500 and 600-numbered wing will be renovated, then the 100-200 wing will be demolished and a new media center and north gym will be built.

Last week some trusses were blown down by high winds, but no one was injured.